Proceanic Engineering Malaysia Sdn Bhd carried out a conductor installation inspection of 14 conductors for the new Kinabalu Platform KNDW-D. The inspection was completed using a PRO4 mini-ROV fitted with underwater camera for real time inspection of the conductor installation. Six (6) normal/ straight and Eight (8) deviated conductor installation were inspected.
- Conductor Driving Inspection (14 Conductors)
- Conductor pre-Drive Heading Verification
- Platform structure base Inspection